The plan of the installation at 6th October 2004.

Below is the plan of the installation as it was envisaged on 23rd September 2004. Notice the differences in the revised plan which now includes indications about the "interactors", the actors who you meet on your journey, and the following general improvements.
• We have now combined the entrance and exit so that visitors get a last look at the River Walk and the Green Man sculptural wall on their way out of the event.
• The decking from the River Walk now continues into the Hawkstone Experience so as to create a more distinct performance area and to give the sense of going down into the caves when you leave via the Troll's Bridge.
• The Symphonic Caves have been given specific qualities and a set of tasks you have to do to continue have been devised.
• The area for the Chromatic Fields and the Sonic Sculpture has been enlarged so we can accommodate larger groups of people there, putting some flexibility into the throughput.
• From a technical point of view the revision gives us a single backstage area which is accessible without crossing any public pathways.
• The raised decking is now in just two locations and provide a safe and efficient means of putting services anywhere into the site.